Please note: this guide is general information to help with planning. Every project is different: always follow your structural engineer’s design, the manufacturer’s instructions and the current Building Regulations.
What a padstone does
A padstone is a solid concrete bearing block placed beneath the end of a steel beam, RSJ or lintel where it sits on a wall. Beams concentrate their load over a small area; the padstone spreads that load over a larger area of masonry so the bricks or blocks beneath are not overstressed or crushed.
Padstones are common in knock-throughs, extensions, loft conversions and anywhere a new beam bears onto existing or new masonry.
When you need a padstone
Whether a padstone is needed, and its size, is decided by your structural engineer. Padstones are typically specified where:
- A steel beam or RSJ bears onto masonry
- A lintel carries a heavy or concentrated load
- The wall beneath is lightweight blockwork or of limited strength
- The load arriving at the bearing is high, for example from floors and roofs above
What decides the size of a padstone
The load
The total load the beam delivers to each bearing, from walls, floors and roofs above.
The bearing length
How far the beam sits onto the wall. The padstone must be long enough to give the bearing length in the design.
The wall beneath
The type and strength of the masonry supporting the padstone. Weaker masonry needs a larger padstone to spread the same load.
The beam size
The padstone must be at least as wide as the beam flange and suit the wall thickness.
There is no single standard size that suits every opening. Always use the padstone dimensions in your engineer’s calculations.
Read more in what size padstone do I need?
Precast concrete padstones
Southcrete manufactures precast concrete padstones to order, in standard or fully bespoke sizes, matched to the length, width and depth on your engineer’s drawings. Precast padstones arrive ready to install, with no waiting for in-situ concrete to cure in the wall.
Installation
- Check the bearing: the wall beneath must be sound and built to the design.
- Bed the padstone on mortar, level and true, in the position shown on the drawings.
- Centre the beam on the padstone, with the bearing length shown in the design.
- Pack and support the beam as specified, and allow mortar to gain strength before full load is applied.
- Keep temporary supports in place until the engineer’s sequence allows them to be removed.
Temporary propping for knock-throughs and openings must be designed and installed by competent people before any load-bearing masonry is removed.
Common mistakes to avoid
- Using a padstone smaller than the size in the calculations
- Placing the beam off-centre or with too little bearing
- Bedding on weak, broken or uneven masonry
- Loading the padstone before the mortar has gained strength
- Substituting a different material without the engineer’s agreement
What to send for bespoke padstones
Send your engineer’s calculations or drawings showing each padstone’s length, width and depth, plus the quantity of each size. Southcrete will manufacture to that schedule and deliver by HIAB, ready to install.