The project

Tony was building a pair of semi-detached homes in Maidstone, Kent, and needed beam and block ground floors for both. He came to Southcrete through his builders’ merchant after another beam and block company had failed to get the drawing right.

The challenge

Time had already been lost, and Tony was working to a deadline. To avoid holding up the build, he needed a correct floor layout drawn, approved and the beams delivered to site within seven days.

That left no room for another round of mistakes. The layout had to be right first time, covering both homes and working around the drainage coming up through the floor.

Our solution

Our in-house estimators got straight onto it and had the floor layout drawing completed within a morning, with every beam set out to suit the spans, loads and bearings across both homes and the drainage positioned exactly where the plan showed.

Tony checked it and signed it off the same afternoon. The beams went straight into production at our depot in Erith, were labelled to match the plan, and were delivered to site in Maidstone on our HIAB crane lorries within the seven days.

The result

Both ground floors went in to plan, with no delays to the project. What had started as a problem with another supplier ended with the floors laid on time and the build moving again.

Tony was very grateful for the speed and the accuracy of the drawing, and he has told us he will be coming back to Southcrete, with plenty of notice this time, for the next two homes on the plot.

Project photos

Tony was very grateful that we turned the drawing round in a morning and kept his build on programme, and will be coming back to us for the next two homes on the plot.