The project
Giles and Giles were building a new dwelling in Bexley, south-east London, and needed a suspended ground floor that could go in quickly so the build could keep moving. Scott came to Southcrete for a beam and block floor designed, supplied and delivered to site.
The brief
Timing was everything. Scott needed the floor designed, made and on site within a week, without cutting any corners on the design, so the build could keep moving.
Our solution
Our in-house estimators worked straight from the drawings to produce a floor layout plan setting out the position and length of every prestressed concrete beam, with the spans, loads and bearings checked for the new home.
As soon as the layout was confirmed, the beams were manufactured at our depot in Erith, labelled to match the plan and delivered to site on one of our HIAB crane lorries. Bexley is only a short drive from our depot, near Dartford, which helped us turn the job round quickly.
On site, the beams were lifted off by the HIAB and laid out on the damp-proof course to the layout plan, ready for the builder’s team to lay the infill blocks between them.
The result
From the first look at the drawings to beams on site took under a week. The builder had a clear layout to work to, and the ground floor went down without holding up the rest of the build.
Scott told us he was very happy with the service from start to finish, and he is already looking forward to working with Southcrete again on his next project in Sidcup.